Avalanche Protection at Trans Canada Highway #1
Facts
Project: | Avalanche mitigation for the Trans-Canada Highway #1 at Three Valley Gap |
---|---|
Place: | Three Valley Gap near Revelstoke, BC |
Country: | Canada |
Year: | 2016-2018 |
Customer: | Ministry of Transportation and Infrastructure (MoTI) |
Protected Objects: | Road |
Installed systems: | 11x Wyssen Avalanche Tower, 12 shots each |
Initial Situation
Our solution
In 2016 Wyssen Avalanche Control was awarded the installation of 9 Remote Avalanche Control Systems (RACS) in the Three Valley Gap avalanche starting zones. The terrain is characterized by gully features on a steep and forested rock face which rises nearly vertically from the highway. The exposure of the highway to avalanches and rockfall in Three Valley Gap is significant. Working in the terrain at the planned tower locations was very challenging due to rockfall, proximity to the highway and the requirement for rope access at most locations. The allowed highway closure times were short to keep the traffic flowing since the fastest detour for traffic takes six hours. After extensive preparation, Wyssen successfully installed four avalanche towers in a four-week period. Five more avalanche towers were installed in summer 2017 followed by two more towers in 2018.
Operational experience
Closure times
Worker safety
Worker resources
A Project of: